How it is worked out
Volume is length times width times thickness for each slab, plus your waste allowance for uneven ground and spillage. The bag count assumes about 45 bags of 80 lb for each yd³ of concrete.
How our concrete takeoff service works →Common questions
How much extra concrete should I order?
Add 5% for a level, formed slab and 10% where the ground is uneven or the edges are dug rather than formed. Running short mid-pour costs far more than a little left over.
Can you measure the concrete from my plans?
Yes. Send the PDF plans and Sigma Build measures slabs, thickenings and footings from the drawings and prices the job at your rates. Concrete is an early-preview trade, so check the takeoff before you rely on it.